AIMS Attachment A: AIMS Statement of Work
Page 15 of 130
Complete installation of all stage two DAPP
airlines, if required
Complete installation of all stage three DAPP
airlines, if required
Complete installation of all stage two CUSS
airlines, if required
Receive Contract Administrator's written
Preliminary Acceptance of Phase Two
1.6.4 Phase Three
Complete installation of AIMS and complete
individual and joint Testing to ensure proper
operation
Receive Contract Administrator written
permission to proceed with Performance
Verification Test
Complete Performance Verification Testing
including items listed below
Complete CONTRACTOR‟s Quality
Assurance organization review of test
procedures
Review against
specifications
Provide finalized Performance Verification
Testing test plan/procedures
Review against
specifications
Conduct and pass all test requirements
Field Verification
against Performance
Verification test plan
(303.2)
Provide finalized Performance Verification
Testing report
Review against
specifications
Complete all remaining training
Complete correction of all AIMS deficiencies
Receive Contract Administrator written
permission to proceed with Endurance Testing
(Stage One airlines only)*
Complete Endurance Testing including items
listed below
Complete CONTRACTOR‟s Quality Control
Assurance Organization review of test
procedures
Review against
specifications
Provide finalized Endurance Testing test
plan/procedures
Review against
specifications
Provide personnel to operate and monitor