AIMS Attachment A: AIMS Statement of Work
Page 126 of 130
3. Environmental conditions.
4. Authority activities in process.
5. Description of all alarm annunciations, responses, corrective actions,
and causes of alarms. Classify as to type of alarm.
6. Description of all equipment failures, including software errors.
7. Description of all maintenance and adjustment operations performed
on system.
8. Daily and weekly tabulations.
9. Daily entries of performance data shall be reviewed by the County‟s
representative designated to observe monitoring of system.
E. The County may terminate testing at any time when the system fails to
perform as specified. Upon termination of testing the CONTRACTOR
shall commence an assessment period as described in Step II.
F. Testing
1. Step I - Initial Testing:
i Time: 24 hours per day for 30 calendar days.
ii CONTRACTOR to make no repairs during this phase unless
authorized in writing by the County.
iii If system experiences no failures, proceed to Step III - Final
Testing.
2. Step II - Initial Assessment:
i After conclusion of Step I or termination of testing, CONTRACTOR
to identify all failures, determine causes, and repair. Submit report
explaining: Nature of each failure, corrective action taken, results
of tests performed to verify corrective action as being successful,
and recommended point for resumption of testing.
ii After CONTRACTOR‟s submission of report, schedule review
meeting at job site. Schedule date and time with the County.
iii At review meeting, demonstrate that all failures have been
corrected by performing Performance Verification Testing.
iv Based on report and review meeting, the County will direct
CONTRACTOR to conclude endurance testing, or proceed to Step
III - Final Testing.
3. Step III - Final Testing:
i Time: 24 hours per day for 30 calendar days.
Exhibit 3
Page 186 of 278